Job Story: Upgrading Shaft Grounding Equipment
Bluepoint Engineering LLC was contracted by Patriot Lines (via Bayonne Dry Dock) to overhaul the propulsion propeller earthing system on the USNS DAHL.
The mission? Replace a worn-out setup with a high-tech, dual-shaft earthing and real-time monitoring system to give the crew live electrical insights.
Vessel: USNS DAHL
Client: Patriot Lines / Bayonne Dry Dock
The Team: 2 Licensed Engineers + 1 Electrical Technician
Phase 1: Out with the Old
- Stripped Down: Removed 2 worn slip rings and 4 grounding brushes.
- Prepped: Deep-cleaned the shafts’ (Port and Stbd) surfaces to make room for the new hardware.
Phase 2: Custom Fabrication & Engineering
The new system came with extra hardware, requiring some quick-thinking engineering:
- Bracket Welding: Fabricated and welded 2 brand-new custom brackets (one per shaft) to support the new monitoring brushes.
- Precision Cutting: Custom-sized and cut heavy-duty copper slip rings right on site for a seamless, continuous track.
- Secured: Fastened the rings tightly using manufacturer-spec metal bands and installed the new brushes.
Phase 3: Wiring & Tech Integration
Our Electrical Technician stepped in to bring the system to life:
- Double Checked: Took continuity readings across multiple points to verify the hardware fit.
- Bilge Wrangling: Navigated the bilge area to install mounting studs and route heavy cabling.
- Panel Power: Mounted and wired the brand-new electrical monitoring panel.
Mission Accomplished
- Tested: Wiring thoroughly verified.
- Secured: All hardware locked down.
- Result: The USNS DAHL sailed out with a fully modernized system, ready to deliver real-time data to her crew.