USCG Shinnecock Gear Repair

Job Story: Twin Disc Reduction Gear Overhaul & Testing

Bluepoint Engineering LLC responded to US Coast Guard Station Shinnecock under Contract to perform targeted repairs and operational testing on a Twin Disc MG507A-1 Reduction Gear system.

  • Vessel / Location: U.S. Coast Guard Station Shinnecock (Hampton Bays, NY)
  • Client: US Coast Guard
  • The Team: Bluepoint Engineers & USCG Engineering Personnel

Phase 1: Selector Assembly Overhaul

  • Valve Repair: Disassembled the selector assembly, removed the worn O-ring, and hand-filed a surface burr on the spool valve until flush before installing a new lubricated O-ring.
  • Spring Replacement: Removed the bottom plate, pressure rise piston, and springs. Replaced both inner and outer compression springs after identifying significant loss of compression pressure in the outer spring.
  • Shim Calibration: Inspected installed shims against technical specifications and OEM guidance, maintaining the baseline configuration for operating pressure verification.

Phase 2: Lube Oil Pump Replacement

  • Removal: Disconnected attached hoses and fittings, then removed the existing lube oil pump along with its gasket and mounting bolts. Cleaned and inspected the mounting face.
  • Installation: Mounted the new lube oil pump using fresh gaskets and hardware, then reconnected the lube oil line.

Phase 3: Testing & Handover

  • Local & Remote Testing: Tested selector engagement locally and from the bridge in both directions. Verified system pressure rapidly climbed to and held at the target 300 PSI normal operating pressure.
  • Restoration & Turnover: Reinstalled the shaft cover, cleaned the engine space, and turned over replaced components and spare shims to station leadership.

Mission Accomplished

  • Tested: Local and bridge engagements verified at 300 PSI operating pressure without issue.
  • Secured: Selector valve, lube oil pump, and housing fully restored and operational.
  • Result: The reduction gear system was successfully restored to service specification and returned to full operational readiness.

Related Job Stories

Phone System Foundation Fabrication & Installation

Bluepoint Engineering LLC was contracted by GBS Group under Customer PO #PO010509 to fabricate and install four custom equipment foundations...

SODERMAN CSW Spool Piece Emergent Repairs

Job Story: Emergency Marine Piping Replacement & ABS Certification Bluepoint Engineering LLC was contracted to attend the MV William A....

DAHL Shaft Earthing and Monitoring

Job Story: Upgrading Shaft Grounding Equipment  Bluepoint Engineering LLC was contracted by Patriot Lines (via Bayonne Dry Dock) to overhaul...